|
|||||||||||||||||||
PAGE THREE |
|||||||||||||||||||
When the towers were completed a temporary cable was stretched between both and a wire mesh gangway built so that workers could start construction of the main cables. This temporary gangway can be seen in the photograph to the right. Workers and machinery pulled the main cables from one tower to the other. |
|||
Once the main cables and the vertical cables were
in position the deck / roadway was fixed hanging below them. This work
took place in 1994. Large purpose built cranes were used to lift the
sections, 4000 tonnes each, were bolted into position, one after
another. 290 sections make up the entire bridge. |
|||
|
THE DECK / ROADWAY NEARING COMPLETION |
||
The final section of the deck was bolted in position in September 1998 and the bridge was opened to the public on the 5th of April of the same year. | |||
CLICK HERE FOR NEXT PAGE ON THE AKASHI-KAIKYO SUSPENSION BRIDGE |
|||
|
|||
|
|||